Shankar Jayavel
Email : civil.shankar AT gmail.com
Professional Summary :
** Technically accomplished professional with 15 years of experience with 7 years as project manager in civil & Turnkey interior Project.
** Having rich working experience in handling projects like Residential, Commercial, Major IT office space, Banking sector, Auditorium projects, Metro project.
** Handling end to end project responsibilities such as Budgeting, procurement, billing, project execution, safety, quality etc.,
** Proven ability to recruit high performance subcontractors and coordinate diverse team of architects, engineers with solid background in Client Relations.
** Awarded with best performer award in Godrej Interio & “Utthama Surakash Puraskara” award from National Safety Council in the year 2019.
Core Strength :
** Expert in project management by ensuring the project on-time completion, profitability, quality & safety.
** Excellent communicator with good amount problem solving skills and activities in high pressure environments with tight deadlines.
** Accomplished leader capable in motivating the team on their strength and making them to executing the project with full potential.
** Hands in executing multi-projects/ multi-locational projects and completing on time,
Experience Details :
Godrej and Boyce Mfg. Co. Ltd. May’14 to current.
Role :Associate Chief Manager (2022 -present)
Role :Senior Manager (2019-2022)
Role :Manager (2017-2019)
Role :Deputy Manager (2014-2017)
Projects Handled :VATech Wabag, Equitas, Syngene, Aircel, NCSCM, Mitsubishi, BMRCL, IKEA–Chennai &Bangalore
Responsibilities Handled :
** Experience in handling large projects of total value more than 202 crores and area of more than 35 lac sft including all sectors.
** Managing projects from start to finish in line with project requirement that include budgeting, planning, execution, procurement, safety, quality, completion, reconciliation etc.,
** Managing a team of 4 Project Manager’s across state for delivering total project on time and within budget.
** Define clear roles and responsibilities and deliverable requirements in terms of scope, schedule, cost, quality to all the team members.
** Preparing and monitoring project related trackers for tracking schedule, productivity, billing, drawings, approvals, RFI etc.,
** Co- ordinate with the design team at the site to ensure that all GFC drawings & material approvals are brought in as per schedule.
** Manage and oversee the day-to-day construction progress of the projects with proper review mechanism.
** Coordinating with Architect team and Clients to focus on adding up latest and innovative materials available in the market.
** Detail estimation on the monthly billing projection and achieving the same every month inspite of uncertainties.
** Preparation of work breakdown structure, Mobilization of resources, monitoring the progress, attending project review meetings, Reconciliation and Certification of final bills of contractors, suppliers, vendors.
** Working on new strategies and increasing project margin by at-least 5-8% than budgeted.
** Promoting safety culture at work place by coordinating with Safety head adhering to company safety standards.
Highlights :
** Achieved best project manager award twice in GODREJ Interio for the year 2017 & 2020.
** Received BMRCL order for 187 Crs by handling the additional role of Business development and also executing.
** Handed over 48 branches of Equitas bank (multilocational) within 4 months.
Shapoorji & Pallonji Co.
Ltd. May'12 to April’14 :
Role :Senior Engineer
Project : Residential towers - DLF garden city.
Responsibilities Handled :
** In-charge for Tower -2 & 3 to complete the entire scope of finishing works involved.
** Coordinated with supervising engineers, contractors, staffs and made the process clear
** Managed all activities like all kind of flooring, painting, false ceiling, plumbing, FAS & FPS by coordinating with the respective contractors.
** Project tracking, Strategic planning for operations goals and integration of resources.
** Participated in client meetings to derive better solutions for project issues.
** Determine needed resources (manpower, equipment and materials) from start to finish with attention to budgetary limitations.
** Achieving the given weekly targets given as per the project requirements.
** To ensure verification and Certification of Sub Contractor’s bills & preparation of client measurements.
** Providing Engineering solution for starting program and translating project ideas into clear plans.
Highlights :
Received best Project Engineer award in Shapoorji Pallonji in the year 2013 for handing over of 68 flats to customers in a span of 6 months.
Shoba Developers Limited, Chennai. Aug'10 to May’12 :
Role :Asst. Engineer
Project : Food Court & Corporate office-Infosys.
Responsibilities Handled :
** Measurement preparation of sub-contractors and preparation of interim payment certifications.
** Inspected project sites to monitor progress and adherence to design specifications, safety protocols and state sanitation standards.
** Coordinate with various subcontractors like HVAC, MEP, IBMS, Fire Fighting, Integrated Environmental Solution (IES)
** Allocate work to other members of team in order to ensure delivery of design to quality, time and budget.
** Establishing and maintaining the all scheduling, cost change controls for this in conjunction with the clients
** Attending the project review meeting and highlighting the requirements needed for completion.
** Estimated quantities and cost of materials, equipment and labor to determine project feasibility.
IVRCL Infrastructures & Projects Ltd, Hyderabad. May'07 to Jul’10 :
Role : Asst.Engineer
Project :Koilsagar Lift Irrigation & Admin block.
Responsibilities Handled :
** Checking the weekly and monthly progress, dealing with consultant, reporting the project manager.
** Caring out civil works for administrative blocks and pump rooms.
** Allocating the equipment’s & resources for the planned target.
** Working on drilling patterns & blasting plan for tunnel escavations.
** Achieving the targeted distance of tunnel excavation with retaining concrete walls.
** Man hour calculation and time management for targets as per schedule.